A rigging plan is developed every time a heavy load is being lifted. The basic idea behind a rigging plan is to have control and establish safety precautions. It is an important planning process that will identify all hazardous situations that might be encountered during lifting.

Types of Rigging Plans

The first step when conducting a rigging safety plan is to identify the type of lift. There are three major classifications of lifting plans: Critical lifts, ordinary lifts, and pre-engineering lifts. Depending on the type of lift, then the rigging plan will have different concepts under evaluation to determine the steps needed to complete a safe rigging and lifting process.​

Rigging and Lifting Plan Components

Once the evaluation process has determined the type of rigging and lifting plan needed, you will need to identify and gather information on the following components:

The rigging equipmentShackles, turnbuckles, and slings being usedThe weight being liftedCenter of gravity of the load being liftedCrane capacity and crane chartsHeight, width, and length of the liftAtmospheric and environmental conditions when the process is being performedEdges and corners of the load. It is important to evaluate all the geometry of the item being liftedSling anglesLoad angle factorFloor loading capacityHow to rig the load using good rigging practicesIdentify and make sure that the attachment points and load can withstand the forces created by the rigging gear attachmentWork zone safetyEvaluate hazards to determine consequences resulting from a collision, upset, or dropping the load

Ordinary Lifts 

Ordinary lifts are the easiest ones to handle. They will normally require a verbal planning process and preliminary lifting and rigging meetings. Only a minimal documentation and evaluation process is needed, but always being sure that all safety precautions are been taken.

Critical Lifts

Critical lifts need a more detailed plan before execution. This process will normally require a written procedure and approval process.

Pre-Engineering Lifts

These are the most challenging ones to deal with. They will require specific rigging points, lifting procedure and identification of components that will probably need to be managed separately, to avoid problems, and minimize potential issues.

Rigging Plan Execution

Once the plan has been established, you will need to follow it closely to reduce the probability of an accident. It is important to

Verify all equipment, fixtures, and accessories before starting Verify that all equipment has been properly inspected and that such inspections are valid. Identify a load manager or a rigging leader. It can be your safety professional or ordinary lifts, assign a designated leader; for critical lifts, assign a person-in-charge (PIC) Conduct a pre-use inspection and verify that all components are in good condition. Conduct a dummy rigging process following the pre-established rigging plan. Be sure to identify and train all workers participating in the process. Clear or prepare the area where the load is being placed or moved Survey the lift site for hazardous or unsafe conditions Clear lift path of obstructions Identify the crane operator Follow specific instructions/procedures for attachment of the rigging gear to the load. Use proper rigging techniques. Stop the job when any potentially unsafe condition is recognized

A rigging plan is developed every time a heavy load is being lifted. The basic idea behind a rigging plan is to have control and establish safety precautions. It is an important planning process that will identify all hazardous situations that might be encountered during lifting.

Types of Rigging Plans

The first step when conducting a rigging safety plan is to identify the type of lift. There are three major classifications of lifting plans: Critical lifts, ordinary lifts, and pre-engineering lifts. Depending on the type of lift, then the rigging plan will have different concepts under evaluation to determine the steps needed to complete a safe rigging and lifting process.​

Rigging and Lifting Plan Components

Once the evaluation process has determined the type of rigging and lifting plan needed, you will need to identify and gather information on the following components:

The rigging equipmentShackles, turnbuckles, and slings being usedThe weight being liftedCenter of gravity of the load being liftedCrane capacity and crane chartsHeight, width, and length of the liftAtmospheric and environmental conditions when the process is being performedEdges and corners of the load. It is important to evaluate all the geometry of the item being liftedSling anglesLoad angle factorFloor loading capacityHow to rig the load using good rigging practicesIdentify and make sure that the attachment points and load can withstand the forces created by the rigging gear attachmentWork zone safetyEvaluate hazards to determine consequences resulting from a collision, upset, or dropping the load

Ordinary Lifts 

Ordinary lifts are the easiest ones to handle. They will normally require a verbal planning process and preliminary lifting and rigging meetings. Only a minimal documentation and evaluation process is needed, but always being sure that all safety precautions are been taken.

Critical Lifts

Critical lifts need a more detailed plan before execution. This process will normally require a written procedure and approval process.

Pre-Engineering Lifts

These are the most challenging ones to deal with. They will require specific rigging points, lifting procedure and identification of components that will probably need to be managed separately, to avoid problems, and minimize potential issues.

Rigging Plan Execution

Once the plan has been established, you will need to follow it closely to reduce the probability of an accident. It is important to

Verify all equipment, fixtures, and accessories before starting Verify that all equipment has been properly inspected and that such inspections are valid. Identify a load manager or a rigging leader. It can be your safety professional or ordinary lifts, assign a designated leader; for critical lifts, assign a person-in-charge (PIC) Conduct a pre-use inspection and verify that all components are in good condition. Conduct a dummy rigging process following the pre-established rigging plan. Be sure to identify and train all workers participating in the process. Clear or prepare the area where the load is being placed or moved Survey the lift site for hazardous or unsafe conditions Clear lift path of obstructions Identify the crane operator Follow specific instructions/procedures for attachment of the rigging gear to the load. Use proper rigging techniques. Stop the job when any potentially unsafe condition is recognized

A rigging plan is developed every time a heavy load is being lifted. The basic idea behind a rigging plan is to have control and establish safety precautions. It is an important planning process that will identify all hazardous situations that might be encountered during lifting.

Types of Rigging Plans

The first step when conducting a rigging safety plan is to identify the type of lift. There are three major classifications of lifting plans: Critical lifts, ordinary lifts, and pre-engineering lifts. Depending on the type of lift, then the rigging plan will have different concepts under evaluation to determine the steps needed to complete a safe rigging and lifting process.​

Rigging and Lifting Plan Components

Once the evaluation process has determined the type of rigging and lifting plan needed, you will need to identify and gather information on the following components:

The rigging equipmentShackles, turnbuckles, and slings being usedThe weight being liftedCenter of gravity of the load being liftedCrane capacity and crane chartsHeight, width, and length of the liftAtmospheric and environmental conditions when the process is being performedEdges and corners of the load. It is important to evaluate all the geometry of the item being liftedSling anglesLoad angle factorFloor loading capacityHow to rig the load using good rigging practicesIdentify and make sure that the attachment points and load can withstand the forces created by the rigging gear attachmentWork zone safetyEvaluate hazards to determine consequences resulting from a collision, upset, or dropping the load

Ordinary Lifts 

Ordinary lifts are the easiest ones to handle. They will normally require a verbal planning process and preliminary lifting and rigging meetings. Only a minimal documentation and evaluation process is needed, but always being sure that all safety precautions are been taken.

Critical Lifts

Critical lifts need a more detailed plan before execution. This process will normally require a written procedure and approval process.

Pre-Engineering Lifts

These are the most challenging ones to deal with. They will require specific rigging points, lifting procedure and identification of components that will probably need to be managed separately, to avoid problems, and minimize potential issues.

Rigging Plan Execution

Once the plan has been established, you will need to follow it closely to reduce the probability of an accident. It is important to

Verify all equipment, fixtures, and accessories before starting Verify that all equipment has been properly inspected and that such inspections are valid. Identify a load manager or a rigging leader. It can be your safety professional or ordinary lifts, assign a designated leader; for critical lifts, assign a person-in-charge (PIC) Conduct a pre-use inspection and verify that all components are in good condition. Conduct a dummy rigging process following the pre-established rigging plan. Be sure to identify and train all workers participating in the process. Clear or prepare the area where the load is being placed or moved Survey the lift site for hazardous or unsafe conditions Clear lift path of obstructions Identify the crane operator Follow specific instructions/procedures for attachment of the rigging gear to the load. Use proper rigging techniques. Stop the job when any potentially unsafe condition is recognized

A rigging plan is developed every time a heavy load is being lifted. The basic idea behind a rigging plan is to have control and establish safety precautions. It is an important planning process that will identify all hazardous situations that might be encountered during lifting.

Types of Rigging Plans

The first step when conducting a rigging safety plan is to identify the type of lift. There are three major classifications of lifting plans: Critical lifts, ordinary lifts, and pre-engineering lifts. Depending on the type of lift, then the rigging plan will have different concepts under evaluation to determine the steps needed to complete a safe rigging and lifting process.​

Rigging and Lifting Plan Components

Once the evaluation process has determined the type of rigging and lifting plan needed, you will need to identify and gather information on the following components:

  • The rigging equipmentShackles, turnbuckles, and slings being usedThe weight being liftedCenter of gravity of the load being liftedCrane capacity and crane chartsHeight, width, and length of the liftAtmospheric and environmental conditions when the process is being performedEdges and corners of the load. It is important to evaluate all the geometry of the item being liftedSling anglesLoad angle factorFloor loading capacityHow to rig the load using good rigging practicesIdentify and make sure that the attachment points and load can withstand the forces created by the rigging gear attachmentWork zone safetyEvaluate hazards to determine consequences resulting from a collision, upset, or dropping the load

Ordinary Lifts 

Ordinary lifts are the easiest ones to handle. They will normally require a verbal planning process and preliminary lifting and rigging meetings. Only a minimal documentation and evaluation process is needed, but always being sure that all safety precautions are been taken.

Critical Lifts

Critical lifts need a more detailed plan before execution. This process will normally require a written procedure and approval process.

Pre-Engineering Lifts

These are the most challenging ones to deal with. They will require specific rigging points, lifting procedure and identification of components that will probably need to be managed separately, to avoid problems, and minimize potential issues.

Rigging Plan Execution

Once the plan has been established, you will need to follow it closely to reduce the probability of an accident. It is important to

  • Verify all equipment, fixtures, and accessories before starting
  • Verify that all equipment has been properly inspected and that such inspections are valid.
  • Identify a load manager or a rigging leader. It can be your safety professional or ordinary lifts, assign a designated leader; for critical lifts, assign a person-in-charge (PIC)
  • Conduct a pre-use inspection and verify that all components are in good condition.
  • Conduct a dummy rigging process following the pre-established rigging plan.
  • Be sure to identify and train all workers participating in the process.
  • Clear or prepare the area where the load is being placed or moved
  • Survey the lift site for hazardous or unsafe conditions
  • Clear lift path of obstructions
  • Identify the crane operator
  • Follow specific instructions/procedures for attachment of the rigging gear to the load. Use proper rigging techniques.
  • Stop the job when any potentially unsafe condition is recognized